Thursday, 4 March 2021

Use recipes to bake better projects

Are your projects unpredictable? Maybe they are a bit like my mother’s cakes!

Better cakes, better projects

My mother wasn’t a great fan of recipes. She had some cookery books, but didn’t always use them. She often baked a cake without using a recipe. Consequently, our family had some great cakes, but also a lot of middling cakes, and a few disasters. Unpredictable.

Does that sound familiar to project managers? Your projects may be a similar mix - few great projects, a lot of middling projects and some disasters.

If your baking was unpredictable, how would you improve it? You would need to start using recipes. And start taking notes on each recipe: “the oven should be at 200°C not 180°C”; or, “this recipe would be better with two eggs". Those notes help you tweak the recipe to improve the result. So next time you bake, try using two eggs. Or try baking at 200°C

To improve your projects, you need the same approach. But we’ll talk about processes instead of cake recipes. And we’ll need continuous improvement, instead of tweaks.

The objective is to get your projects under control. You need defined project management processes (your recipes), and you need feedback from real-world projects (that’s your notes suggesting tweaks). Then test out the revised processes in the next projects. That’s a cycle of continuous improvement.

click here to continue reading about 

  • Donald J. Wheeler's Four States of Control

  • W. Edwards Deming's SDCA cycle

  • My recipe for baking better projects


Saturday, 6 February 2021

When standard Project Management life-cycles are surprising

A few years ago, I created a project management software package called TrioProject. The package was quite good, but it had a major flaw. It used a Gate process approach, which was good. But it standardised the Gate processes… and to my great surprise, that proved to be a weakness. The standardised life-cycle was the flaw.

project management lifecycle

It came as a surprise to me, because I've been working on project management standards for decades. It was clear to me that, to improve project management, you need standards. But you have to standardise the right thing. If you over-standardise life-cycles, you are in trouble. I was in trouble.

I'm not the only person to make this mistake. Often, when I talk to PMOs, I discover that they've made the same mistake. I learn that they have a standard life-cycle such as 

  • Charter
  • Initiate
  • Build
  • Test
  • Deliver and Deploy
  • Close

So let's unravel this problem. Where did I go wrong?

A mixture of good and bad ideas

My first good idea was to use a Gate process. The Project is structured as a series of Stages, each separated by a Gate. This is a proven way of working. It splits the project into manageable chunks of work (stages). It allows the project board to control progress (gates).

My second good idea was to standardise the process. In this way, all projects follow the same path. This standardisation enables repetition, which is the basis for continuous improvement.

The flaw - my bad idea - was to over-standardise the process. Every project is different. So a standard life-cycle is overkill. It's a bad idea. The diversity of projects is enormous. In reality, many projects cannot and should not follow a standard process.

When standards become a problem not a solution.

Once you start down the wrong path, standards become a problem not the solution. If every project has to use a standard process then people hit problems:

  • The process doesn't fit the project (square peg in a round hole)
  • The project manager applies the process blindly, without enough thought

Some companies address these problems by multiplying the number of standards.

  • One company used different life-cycles for different sized projects (small, medium, large).
  • A building company used 3 standard processes, for construction, renovation and maintenance projects.

But multiple standards only complicate the problem, they don't solve the problem.

Faced with these problems, other companies give up on standard life-cycles.

How to ensure that standards are good news

The answer is not to reject standardisation. Standardisation is the foundation of continuous improvement and better project management.

But standardisation must recognise that each project is different:

  • Yes, it's a good idea is to use a Gate process.
  • Yes, it's a good idea to standardise the OVERALL process
  • BUT it's vital to understand that each project is DIFFERENT

The way to achieve this is to use project design. For each project, the delivery must be designed, not standardised.

Delivery needs to be designed (not standardised)

Each project is different, and each project needs to be designed.

Project design is an early project activity which works out how to deliver the project. The project team works out how many stages are needed, and what those stages are.

That's the big challenge: every project must deliver differently.

During project design, the project team analyses project delivery and structures it appropriately. They understand their unique challenge, and design their unique solution.

So that's the source of the flaw in TrioProject. It was a mistake to over-standardise project delivery. You cannot decide in advance. Delivery should be DESIGNED and NOT STANDARDISED.

A sandwich of standardisation

The resulting standard project management life-cycle is a sandwich

  • standardise the early parts of the project
  • design delivery (recognising that each project is different)
  • standardise the final parts of the project

This still provides the basis for a repeatable life-cycle. It allows for enough standardisation to enable continuous improvement.

Gate process sandwich

Read my recent book to find out more about Project Design; and learn how to design your next project.

Traps to avoid

Before we finish, here is a reminder of the traps to avoid:

  • don't standardise the number of delivery stages (for example 3 delivery stages)
  • don't standardise the names of delivery stages (for example analysis, build, deployment)

A small project might need only one delivery stage. A larger project might need five delivery stages. A second large project might need five completely different delivery stages.

Build the Project Factory

To sum up, we standardise project management to give a basis of repetition. Standards provide the foundation for continuous improvement and for building a project factory.

But we also recognise that each project is different. We need to reconcile standards and flexibility.

In a forthcoming blog, I'll say more about the Project Factory. Watch this space.

Thursday, 2 April 2020

Toyota is not just a car maker. Are you just a project manager?

Toyota is the home of Lean Manufacturing. In the 50's, Toyota developed the Toyota Production System, which became Lean Manufacturing. All world-class manufacturing today uses Lean.

There's a classic article by Charles Fishman in Fast Company, published in 2006. It analyses continuous improvement at Toyota’s factory in Georgetown, USA.

Lean Manufacturing

Lean means Continuous Improvement

The author argues that Toyota is not just a car maker.

Here's the key quote
Toyota’s Georgetown factory only looks like a car factory. It’s really a big brain–a kind of laboratory focused on a single mission: not how to make cars, but how to make cars better.
The work is threefold: making cars, making cars better, and teaching everyone how to make cars better.
At its best, Toyota adds one more level: It is always looking to improve the process by which it improves all the other processes.

Project Management needs Continuous Improvement, too

Are you just a project manager?
Or are you a Lean Project Manager with a focus on Continuous Improvement
To qualify as a Lean Project Manager, your work would be threefold
  1. Running projects
  2. Improving your project management process
  3. Teaching everyone how to improve your project management process
And are you at your best - do you add one more level? Are you always looking to improve the process by which you improve your project management process?

From Lean Manufacturing to Lean3 Project Management

Toyota makes it appear easy, by building continuous improvement into their culture. Read the Fast Company article to find out how they do it.
You can do the same for your projects. You can build continuous improvement into your Project Management. Read my new book Lean3 Project Management to find out how you can do it.